S.J. AMOROSO Construction, Inc., University of Santa Cruz Bookstore and Student Commons Buildings. Produced post-project time impact requests for settlement.
-
GSA, New U.S. Courthouse, Laredo,Texas.
Performed an independent analysis of $90T delay claim from Contractor via
the internet.
- Frederic R. Harris, Inc., Power
Inn Road & Grade Separation Project, Sacramento. CA. Advised City Project Manager on
schedule delay issues in defense of claim from contractor.
- Shoemate Buildings, Inc.,
Balfour Road Aquatic Center, Brentwood, CA. Developed 11 Requests for
Time Extension for Prime Contractor in new construction of public center
including buildings, pools, and water slide.
- Project Support Group, Ann Arbor,
MI. Performed immediate review of 5 CPM schedules for fitness to
standards and produced extensive write-up in a 6-hour session
- Caltrans State Route 13/24
Interchange Project, Alameda CA, Schedule Delay Analysis on the effects
of 111 Change Orders over 26 Schedule Updates for $10M project.
- Caltrans State Route 242 Median
Widening Project, Concord CA, Claims Avoidance Consultant for scheduling
issues.
- Orangeville Recreation &
Park District, Orangeville, CA: Consulted on scheduling issues on pending
delay claim for construction of $1.5M building and grounds.
- Contra Costa Transit Authority
(CCTA), Walnut Creek, CA: Scheduler and Delay Claim Analyst for CCTA, The
City of Concord, and Caltrans on $0.5M claim for roadwork project at
Highway 242 & Concord Avenue.
- Mercy Methodist Hospital,
Sacramento, CA: Scheduler and Delay Claim Analysis for Mercy Healthcare
Sacramento defending a $1.4M, multi-phase suit and counterclaim.
- CED Lakeside Apartment Project:
Delay Claim Analysis and graphic support for William Ma & Associates
in a breach of contract dispute.
- Long Beach National Guard
Armory Rehabilitation Project: Project Scheduler and Claims Analyst for
the California State Department of General Services, Office of Project
Development and Management (OPDM.)
- Lodi City Hall Renovation,
Lodi, CA: Delay claims preparation for Leslie G. Delbon Company, Inc.
(contractor) on $1M restoration project.
- Bay Area Rapid Transit (BART)
Pittsburg-Antioch Extension, Concord, CA: Project Controls Engineer on
$157M project to construct 7.8 miles of new double track and two stations
with 2,000 parking spaces. Performed extensive delay analysis work.
- Live Oak School District, San
Jose, CA: Delay Claim Analysis and graphic support for various locations
for William Ma & Associates.
- CalTrans Claims Analysis
Project II, Sacramento, CA: Delay Claim Analysis for Walnut Creek Highway
Expansion Construction Project for the State of California Department of
Transportation in defense of a claim from contractor.
- San Juan School District,
Sacramento, CA: Delay Claim Analysis and graphic support for various
locations for William Ma & Associates.
- CalTrans Claims Analysis
Project II, Sacramento, CA: Delay Claim Analysis for Yuba River Bridge
Construction Project for the State of California Department of
Transportation in defense of a claim from contractor.
- California Department of
Corrections, Wasco and Delano Prisons, CA: Project Manager and Claims
Analyst, Responsible for organizing internal efforts and performing
claims analysis for several subcontractor claims in the $1 Million - $4
Million range.
- Santa Clara County Transit, San
Jose, CA: Delay Analysis Consultant for Caltrans on the Guadalupe
Corridor. Established CPM schedules and As-Builts, to include 23
construction Change Orders.
Return to
Ron Winter Consulting LLC Services
-
California State University, Monterey Bay (CSUMB) Tanimura & Antle Family Memorial Library, Monterey, CA. Owner’s representative working for Strategic Construction Management.
-
Monterey Dental Clinic, Monterey, CA. Contractor’s Scheduler working for JMR & Associates, Folsom, CA on Army Corps of Engineers sponsored project.
-
City of Roseville, Water Treatment Plant Expansion – Phase III, Roseville, CA. CM Project Scheduler working for Nolte & Associates representing the City on water treatment facility multi-phase expansion project.
-
City of Manteca, Wastewater Quality Control Facility Project, Manteca, CA. CM Project Scheduler working for ICM Group representing the City on wastewater treatment facility multi-phase expansion project.
-
Sacramento County Airport System, Sacramento, CA. Project Scheduler for Sierra West Group representing the County on a Domestic Water Connection project.
-
Sacramento Regional County Sanitation District, Sacramento, CA. Project Scheduler working for HDR Inc. representing the County on $17M Arden Parallel Force Main project including microtunneling under the American River.
-
Sacramento Regional County Sanitation District, Sacramento, CA. Project Scheduler working for HDR Inc. representing the County on $18M Laguna Interceptor Extension project including microtunneling under a lake.
-
Sacramento Regional Transit, Folsom, CA. CM Project Scheduler and Claims Avoidance working for Hatch Mott MacDonald on light rail transportation expansion.
-
City of Manteca, Wastewater Quality Control Facility Project, Manteca, CA. CM Project Scheduler working for HDR on wastewater treatment facility expansion.
-
County of Sacramento, Construction Management Division, Folsom East 1-B Interceptor and Road Widening Project, Folsom, CA. CM Project Scheduler working for Sierra West Group on sanitation sewer and road widening project.
-
S.J. AMOROSO Construction, Inc., CalPERS Headquarters Expansion Project, Bid Package 5, Sacramento, CA. Project Scheduler for underground parking garage.
-
State Route 99/Jack Tone Road Grade Separation Project, Rippon CA, Project Scheduler for Nolte and Associates rural interchange heavy railroad grade separation (ongoing.)
-
Nordic Industries, Inc., CalPERS Headquarters Expansion Project, Bid Package 4, Sacramento, CA. Project Scheduler for innovate mass excavation and C-B wall project.
-
Nevada Public Works, UNR Medical Building Project, Reno, NV. Project Scheduler for review of construction of new Medical Center building.
- Shoemate Buildings, Inc.,
Balfour Road Aquatic Center, Brentwood, CA. Prepared 7 CPM-analysis time
extension requests on 8-month project.
- City of Sacramento, Power Inn
Rd./RT Grade Separation Project, Sacramento, CA, Schedule Review at the
request of Frederic R. Harris, Inc
- City of Folsom, Highway 50/East
Bidwell Interchange Project, Folsom CA, Project Scheduler for interchange
upgrade project.
- Caltrans State Route 99/Jac
Tone Road Interchange Project, Rippon CA, Project Scheduler for rural
interchange overhaul.
- Nevada Department of
Transportation ReTRAC Project, Reno NV, Principle Scheduler for Nolte and
Associates on heavy rail lowering project through the City of Reno.
- Caltrans State Route 4 East
Widening Project, Pittsburg CA, Project Scheduler on widening &
soundwall project.
- Caltrans State Route 168
Project, Segments 4 & 5, Fresno CA, Project Scheduler on new highway
construction project.
- UNR Student Services Building,
Reno NV, Project Scheduler for the State of Nevada Public Works.
- Caltrans State Route 242 Median
Widening Project, Concord CA, Project Scheduler and Claims Avoidance
Consultant.
- Caltrans State Highway Route
680 Project, Pleasant Hill CA: Special Scheduling Consultant for
scheduling overview review on $1.2M project.
- Mercy Methodist Hospital,
Sacramento, CA: Project Scheduler for Methodist Hospital Expansion
Project reviewing monthly Contract Schedules.
- Long Beach National Guard
Armory Rehabilitation Project: Project Scheduler and Claims Analyst for
the California State Department of General Services, Office of Project
Development and Management (OPDM.)
- GM Dealerships Renovation,
(various sites): Prepared Master Level Schedule and periodic updates for
new dealership construction sites and renovations on the West Coast.
- Bay Area Rapid Transit (BART)
Pittsburg-Antioch Extension, Concord, CA: Project Controls Engineer on
$157M project to construct 7.8 miles of new double track and two stations
with 2,000 parking spaces.
- Exposition Blvd. Extension
Project, Sacramento, CA: Project Scheduler for NOLTE and ASSOCIATES, Inc.
to oversee construction by RGW Construction of roads, railroad, and a
storm sewer pumping station.
- San Francisco Airport - I/O
Ramps Design and Construction Management, San Francisco, CA: Project
Scheduler for Parsons, Brinckerhoff, Quade & Douglas, Inc. / Manna
Consultants, Inc on $10M Design and Construction Services Project.
- Jean Parker Elementary School,
San Francisco, CA: Project Scheduler for 3D International on unusually
constricted building site. The new earthquake proof school was rebuilt on
old school site in downtown San Francisco.
- Kaiser Foundation Hospital,
South Sacramento Medical Center Expansion, Sacramento, CA: Project
Scheduler for Harbison, Mahony, Higgins, Inc. (HMH) on hospital emergency
room/radiology expansion program.
- Secretary of State/State
Archives Building, Sacramento, CA: Project Scheduler for $57M project
working with 3DI to perform scheduling services for State of California
Department of General Services.
- San Francisco New Courts
Building, San Francisco, CA: Project Scheduler to develop and maintain
200-activity schedule for City of San Francisco as Prime Construction
Manager.
- Glendale High School Addition,
Glendale, CA: Project Scheduler and Assistant Construction Manager on new
school addition project. Performed monthly schedule analysis and critical
construction problem solving analysis.
- San Francisco Skilled Nurses
Mental Health Facility, San Francisco, CA: Schedule Analyst to review and
analyze monthly contractor schedule updates.
- San Francisco Waterfront
Transportation Project, San Francisco, CA: Senior Scheduling Engineer,
Responsible for in-depth review of Contractor's Preliminary and Total
Project CPM schedules.
- San Francisco Earthquake Safety
Program, Phase 2, San Francisco, CA: Project Manager, Responsible for
updating and developing project schedules for the various earthquake
building projects, designed and maintained cost loaded CPM schedules.
- BART Colma Station Expansion
Review Project, Colma/Daly City, CA: Project Scheduler, coordinated the
compilation of the entire project-wide schedule. Assisted in the creation
of several individual contracts' schedules. Assisted in the
constructability, concurrent yard operations, and inter-contract
coordination planning.
- California Department of
Corrections, various locations, CA: Senior Scheduling Engineer,
responsible for the development, design, and implementation of the
scheduling system for the $1.3 billion new prison expansion program. Mr.
Winter designed a construction schedule schema, monitored four projects
of 400 activities, and developed a detailed schedule of 4,000 activities.
- Scheduling Department Training
Coordinator, Fluor Engineers, Inc., Irvine, CA: Scheduled for an
engineering design contract to construct facilities on the North Slope of
Alaska.
- Scheduling Engineer, Fluor
Engineers, Inc., Irvine, CA: Scheduled Mobil Oil Refinery refurbishment
project.
Return to
Ron Winter Consulting LLC Services
- Scheduling and Delay Claims Seminar
to State of Nevada Public Works Board. Participants were from a
cross-section of Inspectors, Project Managers, Architects, and Management.
- Hands-on training in Primavera
Project Planner (P3) CPM scheduling software for Nielsen Dillinghan
Builders, San Francisco, CA: Analyzed needs and taught fundamentals and
specialty techniques of schedule construction and updating to the staff
working on the Tenderloin Elementary School construction project.
- Seminar titled,
"Construction Management Scheduling", to Nolte and Associates,
Sacramento, CA: Led an in-house seminar covering issues involved in
writing scheduling specifications for major construction projects.
- Seminar titled, "Schedule
Update Analysis Techniques", to SFIA, San Francisco Airport, CA: Led
a seminar for multi-company assemblage of Scheduling Engineers on how to
perform a monthly schedule update review.
- Seminar titled,
"Inspectors Using the CPM Schedule", ACIA Chapter Meeting,
Sacramento, CA: Explained CPM Scheduling Technique and practical methods
for reading and understanding schedule listings and logic diagram plots.
- San Francisco Earthquake Safety
Program, Phase 2, San Francisco, CA: Hired and trained a Junior Scheduler
to maintain schedules that I created. Managed Scheduler from Sacramento
Office.
- Combined Sewer System
Rehabilitation Program, Sacramento, CA: Taught Engineers in the use of an
Information Tracking and Retrieval System including SWMM modeling
analysis system.
- Oakland Housing Authority,
Oakland, CA: Taught Field Inspectors in the use of a Gridpad
"pen" computerized inspection system for $30T HUD-sponsored
apartment rehabilitation program.
- Los Angeles Full Secondary
Hyperion Wastewater Treatment Plant, Los Angeles, CA: Responsible for the
development and training for the staffing program that was used by
project engineers to assist in their manpower forecast needs over the
life of the 10 year project.
- California Department of
Corrections, various locations, CA: Senior Scheduling Engineer,
responsible for training two other scheduling engineers in the
implementation of the scheduling system for a $1.3 billion new prison
expansion program.
- Marketing Applications
Engineer, Genesis Electronics Corporation (Now called Microlog
Corporation), Rancho Cordova, CA: Developed and taught training classes.
Documented and published product design history. Provided field sales
support.
- Scheduling Department Training
Coordinator, Fluor Engineers, Inc., Irvine: Taught internal company
school for Scheduling Engineers.
- Assistant Scheduling Editor,
Fluor Engineers, Inc., Irvine, CA: Assisted with the design and creation
of the first FLUOR Scheduler's Manual.
Return to
Ron Winter Consulting LLC Services
-
Logic League (tm), developed an extended relationship database manager software.
-
LONGEST PATH Software (tm), developer of concept and implementation to compute and use Longest Path Values for every activity in a schedule.
-
Work Profiler (tm), developer of supper-set of SA Pro software that allows actual daily work records to be incorporated into analyses.
-
Commissioned to develop private automated schedule simulation program for Long International, Inc.
-
Ink Miser, developer of optimizer for P3 group order to clean-up plotted relationship lines.
- Schedule Analyzer Pro Software
Suite, developer of a whole suite of software packages to assist
Claims Developer, Project Scheduler, and Contractor in schedule-related
issues. Functionality of this package is not available anywhere else.
- Schedule Analyzer Software (tm), Designed and programmed state-of-the-art software for automated analysis of CPM Schedule updates in P3 format. Converted original DOS-based software into Windows format using Visual Basic. Windows version released February 1998.
- Glendale High School Addition,
Glendale, CA: Designed, programmed and implemented fully automated
construction management system using Paradox for Windows. Databases
included RFI Log, Meeting Minutes and Issues, CM Daily Log, and Submittal
Log.
- Combined Sewer System Rehabilitation
Program, Sacramento, CA: Working as MIS Task Manager, designed and
oversaw development of an Information Tracking and Retrieval System
including SWMM modeling analysis system. Developed and managed Facilities
plans CADD digitization and field check program.
- Oakland Housing Authority,
Oakland, CA: Designed, and programmed a Gridpad "pen"
computerized inspection system for $30T HUD-sponsored apartment
rehabilitation program.
- Los Angeles Full Secondary
Hyperion Wastewater Treatment Plant, Los Angeles, CA: Working as MIS
Project Manager, designed and implemented the invoicing system utilized
by the City for all consultants on the project.
- California Department of
Corrections (CDC), various locations, CA: MIS Project Manager,
responsible for the design, set-up and implementation of Standard Design
Document Management System Database. Developed and coordinated first
program to archive and distribute design database on CD-ROM.
- Software Engineer, GTE Sprint,
Burlingame, CA: Staff COBOL Programmer for engineering projects on Tandem
minicomputers.
- Scheduling Department Training
Coordinator, Fluor Engineers, Inc., Irvine, CA: Worked as Systems Analyst
to develop in-house IBM 360 critical path scheduling program.
Return to
Ron Winter Consulting LLC Services
Mr. Winter has
over twenty years of experience in Computerized Scheduling, Information
Management, Project Management, and Delay Claims Preparation in technical
construction and manufacturing industries. He has developed and implemented CPM
scheduling and Management Information Systems for an impressive variety of
projects.
Ron Winter has led software project teams and is well versed in the utilization
and programming of most major software.
He has been active in promoting state-of-the-art programming systems to
meet specific project needs such as using Gridpad pen-based computer systems
for data collection and inspections. He has written
specialty computer programs to assist him in performing Delay Claims and
Scheduling tasks quicker, cheaper, and more accurately.
EDUCATION & AWARDS:
-
B.S. General Engineering, University of California at Los Angeles 1974
-
M.S. Systems Management, University of Southern California 1980
-
Advanced Scheduling Concepts, FLUOR Engineers, Irvine, CA 1982
-
Planning and Scheduling Professional (PSP) Certification from the Association for the Advancement of Cost Engineering, International (AACE) June 2004.
-
Technical Excellence Award, from the Association for the Advancement of Cost Engineering, International (AACE) July 17, 2007.
-
Outstanding Technical Committee Chair Award, from the Association for the Advancement of Cost Engineering, International (AACE) June 30, 2009.
-
Outstanding Technical Committee Chair Award, from the Association for the Advancement of Cost Engineering, International (AACE) June 21, 2011.
PUBLISHED PAPERS:
-
Baseline Schedule Checks and Balances, Primavera User’s Conference, San Diego California, October 2002
-
Computing Near-Longest Path, Part 1, Cost Engineering the AACE Journal, January 2003, Vol 45, No. 1
-
Computing Near-Longest Path, Part 2, Cost Engineering the AACE Journal, February 2003, Vol 45, No. 2
-
Automated Schedule Analysis, AACE Western Winter Workshop, Monterey California, March 2003
-
Computing the Near Longest Path, AACE International Conference, Orlando Florida, June 2003.
-
How to befuddle a College Professor (without Really Trying), Cost Engineering the AACE Journal, October 2003, Vol 45, No. 10
-
Review of “Construction Scheduling with Primavera Project Planner”, Cost Engineering the AACE Journal, October 2003, Vol 45, No. 10
-
119 Schedule Update Checks Is a Complete Review, Primavera User’s Conference, Orlando Florida, November 2003
-
P3e/c CPM Calculation Settings, AACE Western Winter Workshop, Monterey California, March 2004
-
Longest Path Value (to the rescue), AACE Southern California Chapter Spring Conference, April 2004
-
Longest Path Value (to the rescue), PMI College of Scheduling Convention, Montreal Canada, April 2004
-
Computing the As-Built Critical Path, AACE International Conference, Washington D.C., June 2004
-
Using Longest Path with Primavera, Primavera User’s Conference, New Orleans, Louisiana, October 2004
-
Managing Resource Leveling, AACE Southern California Chapter Spring Conference, April 2005
-
Extended Relationship Databases, 2nd Annual PMI College of Scheduling Convention, Scottsdale, Arizona, May, 2005
-
Managing Multiple Milestones, AACE International Conference, New Orleans, Louisiana, June 2005
-
Understanding Primavera E&C CPM Calculation Rules, Primavera User’s Conference, Orlando, Florida, November 2005
-
Rules for Determining the Actual Critical Path, 3rd Annual PMI College of Scheduling Convention, Orlando, Florida, April 2006
-
Managing Resource Leveling, Cost Engineering the AACE Journal, July 2006, Vol 48, No. 7
-
Making CPM More Transparent, AACE International Conference, Las Vegas, Nevada, June 2006
-
Proper Implementation of Resource Leveling, 4th Annual PMI College of Scheduling Convention, Vancouver, Canada, April, 2007
-
Recommended Practice on Time Impact Analysis for Schedulers, AACE International Conference, Nashville, Tennessee, July 2007
-
Recommended Practice on Schedule Update Review, AACE International document, Recommended Practice No.53R-06, July 2007
-
Rectification of CPM Schedules, 6th Annual PMI College of Scheduling Convention, Chicago, Illinois, May 2008
-
Subcontractor Scheduling, 6th Annual PMI College of Scheduling Convention, Chicago, Illinois, May 2008
-
Understanding P6 Dates, AACE International Conference, Seattle, Washington, July 2009
-
Rectification of CPM Schedules, AACE International Conference, Atlanta, Georgia, June 2010
-
DCMA 14-Point Assessment Check, the first annual Construction CPM Conference, January 2011.
-
Scheduling for Subcontractors, AACE International Conference, Anaheim, California, June 2011
-
MS Project for Construction Scheduling, AACE International Conference, Anaheim, California, June 2011
PROFESSIONAL