  Below is the entire update history of Schedule Analyzer Professional (SA Pro.) The top line describes the current version. Registered, licensed Users are encouraged to look-up the version of their current SA Pro software and reference the current updates here.
 
Key:
ALL: All SA Pro programs
APAB: SA Pro As-Planned/As-Built Maker (moved to SA Forensic April 2004.)
BASELINE: SA Pro Baseline Checker (released December 1997.)
DASHBOARD: SA Pro Dashboard (added May 2006.)
DATECALC: Date Calculator (released December 1997.)
LOGGER: SA Pro Schedule Logger (released December 1997.)
LOGIC: SA Pro Logic League (released 2003)
LONGPATH: SA Pro Longest Path (added April 2004.)
DESTATUS: SA Pro As-Built Critical Path (moved to SA Forensic April 2004.)
PLANNER: Resource Planner (added February 2005.)
PROFILER: SA Profiler Profile Maker (moved to SA Forensic April 2004.)
REBUILD: SA Pro Rebuilder (moved to SA Forensic April 2004.)
SAPRO: SA Pro Menu Program (released December 1997.)
UPDATE: SA Pro Update Checker (released December 1997.)
WORK: SA Profiler Work Schedule (moved to SA Forensic April 2004.)

CURRENT VERSION:
Version 4.07 (July 2008)
OVERVIEW: LONGEST PATH SOFTWARE IMPROVEMENTS.
SCHEDULE: Fixed formatting of Deleted Historical Relationships report.
LONGPATH: Updated CPM calculation for negative lag activities that have an Actual Start but not an Actual Finish.
LONGPATH: Moved optional CPM calculation output to My Documents.
Version 4.06 (June 2008)
OVERVIEW: IMPROVED THE ACTIVE REPORTS FEATURE.
SCHEDULE: Prevent Error 5 while using Active Reports.
Version 4.05 (April 2008)
OVERVIEW: IMPROVEMENT ON LONGEST PATH PROCESSING TIME.
LONGPATH: Improved processing speed in Slack Calculation section.
BASELINE: BASELINE: Eliminate Error 6 in Duplicate Activity Descriptions section.
Version 4.04 (March 2008)
OVERVIEW: IMPROVED ERROR CHECKING.
LONGPATH: Fixed error caused by completed activities without dates.
Version 4.03 (March 2008)
OVERVIEW: ALLOWED BASELINE CHECKER TO DEAL WITH POORLY-MADE MEGA-SCHEDULES.
BASELINE: Prevent internal overflow error in the Activity Check section.
BASELINE: Added Report bustout ability for very large schedules.
Version 4.02 (February 2008)
OVERVIEW: MINOR REPORT CORRECTIONS.
SCHEDULE: Corrected Average Float calculation.
BASELINE: Minor Diagnostic Report format corrections.
Version 4.01 (February 2008)
OVERVIEW: IMPROVED PERFORMANCE OF ACTIVE REPORTS.
ALL: Active Reports now works even if P3 screen is "locked" in activity edit mode.
Version 4.00 (January 2008)
OVERVIEW: MOVED LOGIC LEAGUE TO THE SA PRO PACKAGE.
LOGIC: Added Logic League. Major usability reconditioning of the product.
ALL: Moved application data files to correct Windows locations.
SAPRO: Improved video display.
BASELINE: Moved option to designate reporting directory to Setup.
UPDATE: Moved option to designate reporting directory to Setup.
ALL: Numerous small enhancements to improve performance and display.
UPDATE: Added Average Total Float calculation.
UPDATE: Added ability to limit the number of lines in the ODD TOTAL FLOAT Report.
Version 3.60 (December 2007)
OVERVIEW: LAST VERSION 3 SOFTWARE UPGRADE. MINOR CHANGES.
BASELINE: Fixed "Review Tips" button functionality.
All: Restricted running Active Reports function unless User double-clicks on an Activity Line.
Version 3.59 (November 2007)
ALL: Added Copy Activity ID and Copy Full Activity to View Edit menu.
BASELINE: Added View Window useage tip at startup.
UPDATE: Added View Window useage tip at startup.
ALL: Fixed Active Reports Video Help button.
ALL: Added Copy Activity Help video.
Version 3.58 (October 2007)
UPDATE: Modified NEWLY COMPLETED ACTIVITIES WHICH FINISHED LATER THAN EXPECTED Report.
UPDATE: Modified NEWLY COMPLETED ACTIVITIES WHICH FINISHED EARLIER THAN EXPECTED Report.
UPDATE: Modified format for Suspend/Resume reports.
LONGPATH: Fixed automatic re-run of Longest Path procedure.
Version 3.57 (October 2007)
ALL: Automatically generate SA_ERROR.TXT from diagnostics screen on error.
Version 3.56 (September 2007)
UPDATE: Added the ACTIVITIES WITH NEW ACTUAL DATES THIS PERIOD Report.
LOGGER: Added the ACTIVITIES WITH NEW ACTUAL DATES THIS PERIOD Report.
UPDATE: Added the NEW PERCENT COMPLETE THIS PERIOD Report.
LOGGER: Added the NEW PERCENT COMPLETE THIS PERIOD Report.
Version 3.55 (September 2007)
UPDATE: Added the NEWLY COMPLETED MILESTONES THIS PERIOD report.
LOGGER: Added the NEWLY COMPLETED MILESTONES THIS PERIOD report.
Version 3.54 (September 2007)
UPDATE: Added more error notification information for bad data date check.
UPDATE: Prevented divide by zero error in the Resource Total Performance Ration Analysis.
UPDATE: Improved accuracy in Milestones with Variances Report.
Version 3.53 (August 2007)
ALL: Allowed for spaces in directory names when shelling to other programs.
Version 3.52 (August 2007)
LOGGER: Fixed Directory Not Found error.
ALL: Allowed user to override P3OUT location with DEFAULT_OUT=
ALL: Report destination prompted for if "?" used at the end of DEFAULT_OUT entry.
UPDATE: Corrected error generated when P3OUT directory contains a long file name with spaces.
Version 3.51 (July 2007)
BASELINE: Fixed error generated after analysis run.
BASELINE: Prevented Error 52 in Cost Section if schedule is in hours instead of days.
Version 3.50 (June 2007)
BASELINE: Select Report added to menu when viewing reports.
DASHBOARD: Select Report added to menu when viewing reports.
UPDATE: Select Report added to menu when viewing reports.
BASELINE: Redesigned and standardized View window with menus instead of buttons.
DASHBOARD: Redesigned and standardized View window with menus instead of buttons.
UPDATE: Redesigned and standardized View window with menus instead of buttons.
BASELINE: Added Task Tags feature for tagging selected report activities in your P3 schedule.
DASHBOARD: Added Task Tags feature for tagging selected report activities in your P3 schedule.
UPDATE: Added Task Tags feature for tagging selected report activities in your P3 schedule.
ALL: Switched over to Windows Video Player for Vista compatibility.
Version 3.49 (June 2007)
UPDATE: Added CONSTRAINTS AUTOMATICALLY DELETED WHEN ACTIVITY WAS COMPLETED Report.
DASHBOARD: Added CONSTRAINTS AUTOMATICALLY DELETED WHEN ACTIVITY WAS COMPLETED Report.
DASHBOARD: Improved reporting when reports sections were skipped.
DASHBOARD: Improved speed in Overview Administrative Section requests.
DASHBOARD: Improved error handling on displaying extremely large reports.
DATECALC: Prevented occasional Error 5 problem when adding Holidays.
Version 3.48 (May 2007)
ALL: Smart Copy now lists the title information in the second column and not the last.
LONGPATH: Caught calendar underrun with Start Milestones and Finish-to-start successor relationships.
UPDATE: Limited reporting of PROGRESS ON LONGEST PATH LAST PERIOD Report to uncompleted activities.
Version 3.47 (May 2007)
LONGPATH: Allowed for exceptionally early calendars due to very early actual dates.
LONGPATH: Improved error message for very early dates to indicate schedule file corruption.
LONGPATH: Improved communications timing with P3 with very large schedules.
Version 3.46 (May 2007)
ALL: Re-wrote help files system.
All: Changed Help File System over to HTML to meet Vista standards.
ALL: Added new Help/About serial number system.
Version 3.45 (April 2007)
LONGPATH: Fixed "Calendar ID ? is not defined." error.
BASELINE: Check for not using the default activity calendar.
Version 3.44 (April 2007)
ALL: Improved Active Reports accuracy when reporting on a successor activity.
UPDATE: Added Resource Total Time Ratio Report.
UPDATE: Added Activity Codes Check.
UPDATE: Added Activity Codes TTR Report.
DASHBOARD: Added Resource Total Time Ratio Report.
DASHBOARD: Added Activity Codes Check.
DASHBOARD: Added Activity Codes TTR Report.
Version 3.43 (April 2007)
LONGPATH: Extensive re-write to make processing faster.
LONGPATH: Added check to warn about Progress Override being used.
LONGPATH: Added check to warn about Interruptible Activities being used.
LONGPATH: Added in-memory indexing for faster analysis.
PLANNER: Prevented error when leveling report contains CPM report as well as leveling report.
Version 3.42 (March 2007)
UPDATE: Fixed label for Optional Report 4 in High Level Analysis options list.
ALL: Added external video player option (needed for Vista.)
ALL: Upgraded software loading program for Vista compatibility.
All: Tested for Windows Vista compatibility.
Version 3.41 (February 2007)
BASELINE: Prevented Error 53 in Code Check Section when no codes are defined.
UPDATE: Fixed truncated calendar descriptions.
Version 3.40 (January 2007)
BASELINE: Improved handling in Active Reports.
DASHBOARD: Improved handling in Active Reports.
UPDATE: Improved handling in Active Reports.
LONGPATH: Added help message for a P3 access problem.
BASELINE: Added Print Section guidance message.
DASHBOARD: Added Print Section guidance message.
UPDATE: Added Print Section guidance message.
Version 3.39 (December 2006)
LONGPATH: Greatly speed-up calculation of CPM.
LONGPATH: Overall improvement in responsiveness to other programs running at the same time.
ALL: Increased responsiveness to user inputs while running.
UPDATE: Fixed Error 13 in PROGRESS ON LONGEST PATH LAST PERIOD report.
DASHBOARD: Made Video Help more prominent.
DASHBOARD: Put the title of the report in the program title bar.
Version 3.38 (November 2006)
BASELINE: Added ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS report.
LOGGER: Added ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS report.
DASHBOARD: Added ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS report.
DASHBOARD: Fixed formatting error in Relationship Section.
Version 3.37 (November 2006)
UPDATE: Internally retained report name after printing or view.
UPDATE: Fixed problem with viewing report with more than 32,000 lines.
BASELINE: Provided option to save working files.
Version 3.36 (October 2006)
UPDATE: Added notes to Due Diligence and Early Starts Reports.
BASELINE: Added calendar check to Review Activities Report.
SA Pro: Added Welcome Video.
Version 3.35 (October 2006)
UPDATE: Added Remaining Duration to database.
UPDATE: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES report.
LOGGER: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES report.
DASHBORD: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES report.
UPDATE: Fixed formatting error in PROGRESS ON LONGEST PATH LAST PERIOD report.
BASELINE: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES report.
Version 3.34 (September 2006)
BASELINE: Added context-sensitive View Help for every report.
BASELINE: Updated Manual and Help with comprehensive audit.
BASELINE: Added two new Help Videos to the View Screen.
BASELINE: Added Smart Copy to View menu list
UPDATE: Added context-sensitive View Help for every report.
UPDATE: Updated Manual and Help with comprehensive audit.
UPDATE: Added two new Help Videos to the View Screen.
UPDATE: Added Smart Copy to View menu list
DASHBORD: Added context-sensitive View Help for every report.
DASHBORD: Added two new Help Videos to the View Screen.
DASHBORD: Added Smart Copy to View menu list
Version 3.33 (September 2006)
UPDATE: Improved accuracy in reporting INVALID ADDED RELATIONSHIPS report.
Version 3.32 (August 2006)
ALL: Improved timing & communications with P3.
DASHBOARD: Fixed limits settings.
DASHBOARD: Added ACTIVITIES WITH TOO MUCH FLOAT report.
DASHBOARD: Added ACTIVITIES WITH DELETED ACTUAL DATES report.
DASHBOARD: Added PROGRESS ON LONGEST PATH LAST PERIOD report.
DASHBOARD: Added ADDED ACTIVITIES MISSING SUCCESSORS report.
Version 3.31 (August 2006)
UPDATE: Improved PROGRESS ON LONGEST PATH LAST PERIOD report.
LOGGER: Modified PROGRESS ON LONGEST PATH LAST PERIOD report.
Version 3.30 (August 2006)
UPDATE: Added ADDED ACTIVITIES MISSING SUCCESSORS report.
LOGGER: Added ADDED ACTIVITIES MISSING SUCCESSORS report.
Version 3.29 (August 2006)
UPDATE: Added PROGRESS ON LONGEST PATH LAST PERIOD report.
LOGGER: Added PROGRESS ON LONGEST PATH LAST PERIOD report.
Version 3.28 (July 2006)
BASELINE: Fixed ability to hide "Finished" dialogue box.
UPDATE: Fixed ability to hide "Finished" dialogue box.
UPDATE: Added ACTIVITIES WITH DELETED ACTUAL DATES report to reinforce existing MODIFIED report.
LOGGER: Added ACTIVITIES WITH DELETED ACTUAL DATES report.
Version 3.27 (June 2006)
BASELINE: Added ACTIVITIES WITH TOO MUCH FLOAT report.
LOGGER: Added ACTIVITIES WITH TOO MUCH FLOAT report.
Version 3.26 (June 2006)
UPDATE: Fixed formatting error in MODIFIED ACTIVE RELATIONSHIP LAGS report.
SAPRO: Fixed Resource Planner button.
BASELINE: Added first-time help screens.
UPDATE: Added first-time help screens.
LONGPATH: Updated both user help videos.
Version 3.25 (May 2006)
PLANNER: Added User-override for check to see of report matches schedule.
BASELINE: Internal improvements to make program smaller and more efficient.
DASHBOARD: Added new module to Schedule Analyzer.
BASELINE: Added Dashboard access.
UPDATE: Added Dashboard access.
Version 3.24 (April 2006)
ALL: Fixed an installation problem caused by internal software upgrades.
Version 3.23 (March 2006)
ALL: Added ability to work with P3 Password.
UPDATE: Improved Summary Reports.
UPDATE: Further refinements in error checking for Longest Path Report.
UPDATE: Restated missing Longest Path reports.
Version 3.22 (February 2006)
UPDATE: Improvements made in saving User Settings.
BASELINE: Improvements made in saving User Settings.
BASELINE: Reversed indicated condition for HAMMOCK ACTIVITIES MISSING REQUIRED RELATIONSHIPS report.
UPDATE: Shortened the verbal clue after the first time when copying to clipboard.
Version 3.21 (January 2006)
UPDATE: Improved error handling throughout.
PLANNER: Improved error handling.
UPDATE: Prevent Invalided Added Relationships report from improper reporting of Milestones
UPDATE: Prevent flashing of screen in Due Diligence Report.
UPDATE: Longest Path Report for statused target schedule modified.
SAPRO: Fixed menu buttons that had "Cannot Find Program" error.
UPDATE: Added float readings to DELETED RELATIONSHIPS Report.
UPDATE: Fixed missing summary line on ACTIVE DELETED RELATIONSHIPS Report.
Version 3.20 (November 2005)
UPDATE: Added INVALID ADDED RELATIONSHIPS (DUE TO STATUS) Report
UPDATE: Fixed minor internal relationship match flagging error.
UPDATE: Fixed Relationship Reports minor lag formatting error.
UPDATE: Improved added relationship-pairs reporting accuracy.
DATECALC: Added Save as Spreadsheet function.
Version 3.19 (October 2005)
BASELINE: Resized program to accept 35,000 activity schedules.
UPDATE: Resized program to accept 35,000 activity schedules.
Version 3.18 (August 2005)
LOGGER: Added Help button to "Select Target Schedule" window.
UPDATE: Added current printer name to print in OK message.
UPDATE: Corrected minor formatting error in ACTIVITIES WITH MODIFIED RELATIONSHIPS report.
Version 3.17 (July 2005)
UPDATE: Added Active Reports to jump straight to the designated P3 activity from the report.
BASELINE: Added Active Reports to jump straight to the designated P3 activity from the report.
Version 3.16 (June 2005)
UPDATE: Added Statused Target Schedule Longest Path report (LP if no logic changes made.)
LONGPATH: Added status indications to show progress.
UPDATE: Deleted relationships status used to be based on Target Dates. Now Update Dates are used instead.
BASELINE: Reduced over-reporting of submittal activities without review activities.
BASELINE: Prevent Finish Milestone over-reporting in EARLY ACTIVITIES NOT LOGICALLY TIED TO NOTICE TO PROCEED report.
Version 3.15 (June 2005)
UPDATE: Fixed Out of Sequence Progress Check error when target directory is not update directory.
UPDATE: Improved Actual Dates accuracy.
UPDATE: Added Remaining Duration to database (preparing for new features.)
UPDATE: Added Target Out-of-sequence check.
UPDATE: Fixed Error 6 problem in High-level Checks Section and very large schedules.
Version 3.14 (May 2005)
UPDATE: Removed completed activities out of Active Historical Out-Of-Sequence List.
ALL: Corrected "NOSPLASH" bug when no P3 User Id is entered.
BASELINE: Corrected Submittals Without Review over-reporting for lower-case descriptions.
Version 3.13 (April 2005)
UPDATE: Added checks and cautions to Suspended/Resume dates reports to check for dates in the future.
UPDATE: Corrected Cost section error caused by a Version 3.12 addition.
ALL: Improved "Copy" sound-queue.
Version 3.12 (March 2005)
ALL: User interface standardization.
BASELINE: Modified SUBMITTAL ACTIVITIES WITHOUT SUCCESSOR REVIEW ACTIVITIES report to also note Spanish text and avoid false positives.
UPDATE: Changed sign of float change amount in ACTIVITIES WITH ODD TOTAL FLOAT CHANGE.
UPDATE: Improved formatting of the second line of Added Relationship reports.
UPDATE: Added ACTIVITIES THAT STARTED OUT-OF-SEQUENCE THIS PERIOD report.
UPDATE: Added HISTORICAL ACTIVITIES THAT CONTINUE TO RUN OUT-OF-SEQUENCE report.
Version 3.11 (February 2005)
UPDATE: Fixed problem with occasional failure to find the help file.
BASELINE: Fixed problem with occasional failure to find the help file.
DATECALC: Added optional ticker-tape read-out.
SAPRO: Updated menu program to include Resource Planner program.
PLANNER: Added Resource Planner module to Schedule Analyzer
Version 3.10 (January 2005)
UPDATE: Removed remaining duration checking from MODIFIED ACTIVITY RESOURCE Report.
UPDATE: Added RESOURCE REMAINING DURATION CHANGE WITHOUT ACTIVITY CHANGE Report.
Version 3.09 (December 2004)
UPDATE: Added Longest Path flag to Added Relationship Reports.
UPDATE: Added Longest Path flag to Modified Relationship Reports.
UPDATE: Added ACTIVE RELATIONSHIPS DELETED report
UPDATE: Added ACTIVE RELATIONSHIPS ADDED report.
UPDATE: Added MODIFIED ACTIVE RELATIONSHIPS report.
UPDATE: Added MODIFIED ACTIVE RELATIONSHIP LAGS report.
UPDATE: Added RELATIONSHIPS DELETED BEFORE TARGET DATA DATE report
UPDATE: Added RELATIONSHIPS ADDED BEFORE TARGET DATA DATE report.
UPDATE: Added MODIFIED RELATIONSHIPS BEFORE TARGET DATA DATE report.
UPDATE: Added MODIFIED RELATIONSHIP LAGS BEFORE TARGET DATA DATE report.
UPDATE: Added Warnings, cautions, and notes to Relationship reports.
UPDATE: Added WBS Structure Check.
UPDATE: Added a new section for WBS changed dictionary entries reports.
Version 3.08 (December 2004)
SAPRO: Updated documentation to include new Forensic programs.
UPDATE: Don't perform ACTIVE ACTIVITIES WITH NO PROGRESS report if data date did not change.
UPDATE: Don't perform ACTIVITIES WITH ODD FLOAT CHANGE report if data date did not change.
UPDATE: Update Interruptible Activities Report.
UPDATE: Improved Deleted Relationships Report.
Version 3.07 (November 2004)
UPDATE: Added cautions note to Active Activities without Status report.
UPDATE: Fixed Error 12 in calendar section for certain holiday settings.
Version 3.06 (October 2004)
LONGPATH: Increased calendar defaults durations.
LONGPATH: Added calendar re-generation during processing if demanded.
LONGPATH: Bullet-proofed against very short schedules.
BASELINE: Multiple cosmetic changes made.
BASELINE: Accuracy with ACTIVITIES WITH MULTIPLE LOGIC RELATIONSHIPS (NOT SS & FF PAIRS) report improved.
Version 3.05 (October 2004)
BASELINE: Improved responsiveness when shelling out to P3.
BASELINE: Fixed file handling error when running multiple runs.
BASELINE: Added maximum reporting check to Activities with Embedded Blanks check.
UPDATE: Fixed wrong activity description printed in Suspended/Resume Dates.
Version 3.04 (October 2004)
All: Fixed "File Not Found" error when trying view reports not in the C:\P3WIN\P3OUT directory.
LONGPATH: Improved response while processing.
UPDATE: Added check for added holidays in the future.
UPDATE: Fixed cosmetic error in Modified Resources Check report.
Version 3.03 (August 2004)
BASELINE: Protected for View displaying more than 32,367 lines (Error 6, Overflow.)
LONGPATH: More error prevention added for schedule with large out-of-sequence progress.
UPDATE: Improved Newly Completed Activities that Finished Reports
Version 3.02 (July 2004)
UPDATE: Added resource checks.
UPDATE: Exclude Start Milestones from PLANNED ACTIVITIES WITH CHANGED DURATIONS report.
UPDATE: Eliminated over-reporting of MILESTONES AWAITING STATUS due to calendar differences.
LONGPATH: Eliminated Error 6: Overflow
LONGPATH: Fixed error when unusual Imposed Project Finish date confused program.
LONGPATH: Made more responsive to other programs when running.
Version 3.01 (June 2004)
DATECALC: Added calendar 'date-picker'.
BASELINE: Made Activity Distribution Histogram more accurate.
UPDATE: Bullet-proofed Added Relationships report for an odd combination causing over-reporting.
Version 3.00 (April 2004)
LONG PATH: Added Longest Path Software to SA Pro package to match SAe.
APAB: Transferred software to SA Forensics Package.
DESTATUS: Transferred software to SA Forensics Package.
PROFILER: Transferred software to SA Forensics Package.
REBUILD: Transferred software to SA Forensics Package.
WORK: Transferred software to SA Forensics Package.
Version 2.89 (March 2004)
APAB: Made Original Duration = Remaining Duration and Percent Complete = 0 to prevent confusion.
DESTATUS: Multiple updates and improvements made for massively out-of-sequence issues.
Version 2.88 (February 2004)
UPDATE: Added resource checking.
DESTATUS: Increase internal size to prevent Error 6 problem on very large schedules.
DESTATUS: Fixed project not found when multiple directories used.
DESTATUS: Reset old P3 directory back to original setting.
BASELINE: Protected for View displaying more than 32,367 lines (Error 6, Overflow.)
ALL: Fixed "File Not Found" error when viewing reports not in C:\P3WIN\P3OUT directory.
Version 2.87 (February 2004)
ALL: Further bullet-proofed saving of operational parameters.
ALL: Fixed 'NOSPLASH' User ID if set-up wrong when program begins.
Version 2.86 (February 2004)
LOGGER: Fixed bug in Maintenance Copy Logs process.
ALL: Further bullet-proofing for data file requests.
BASELINE: Improved topic checking.
UPDATE: Fixed Earned Value P3 reporting bug adjustment.
Version 2.85 (December 2003)
BASELINE: Bullet-proofed relationship database building.
UPDATE: Bullet-proofed relationship database building.
UPDATE: Bulletproofed Activity section where use of reserved words causes Error 5.
UPDATE: Improved calendar check.
Version 2.84 (November 2003)
UPDATE: Fixed incorrect display of relationship in "Relationships which have been Deleted Since Last Update" Report.
REBUILDER: Fixed Run Button 'sticking' problem.
BASELINE: Added ACTIVITIES ON THE LONGEST PATH report.
BASELINE: Added Longest Path check to Substantial Completion report.
BASELINE: Bulletproofed response for when CPM has not been run.
Version 2.83 (October 2003)
BASELINE: Sized Activity Code Section for more than 32,000 codes.
LOGGER: Improved Maintenance Section.
LOGGER: Fixed copy function to not overwrite existing entries.
LOGGER: Fixed 'missing headers' bug.
BASELINE: Bullet-proofed Activity Code Section Check.
BASELINE: Corrected P3.ini USERFILLOC entry error.
BASELINE: Extended description title check words database.
Version 2.82 (September 2003)
ALL: Added Error Help command button to all main screens.
ALL: SA Pro now remembers your User ID from session to session.
Version 2.81 (September 2003)
UPDATE: Prevent ACTIVITIES WITH PROGRESS BUT NO START DATE report from reporting finish milestones or flags.
UPDATE: PLANNED ACTIVITIES WITH CHANGED DURATIONS report now excludes Original Duration changes and moved to print after the Changed Original Duration Report.
UPDATE: Improved Diagnostics Report.
SCHEUDLE: Improved Added As-Built Activity status reporting.
UPDATE: Added note to NEWLY COMPLETED ACTIVITIES WHICH FINISHED LATER THAN EXPECTED report explaining apparent anomalies.
UPDATE: Made the changed description report check case insensitive.
Version 2.80 (August 2003)
UPDATE: Better analyzes hourly schedules.
BASELINE: Improved Numeric Activity ID check
Version 2.79 (August 2003)
BASELINE: Added some new keywords in topics checks.
BASELINE: Added 1-Day Activity Duration Report.
LOGGER: Fixed processing error for Baseline schedules.
BASELINE: Updated Standards formatting to match Schedule Logger requirements.
DATECALC: Added Move 2nd Date to 1st Date function.
DATECALC: Added Calc 2nd Date from Calendar Days button.
Version 2.78 (July 2003)
BASELINE: Put Version number back in (cosmetic.)
BASELINE: Prevented screen flicker in Unregistered Activity ID Codes Report.
BASELINE: Added maximum report length check to ACTIVITIES WITHOUT A FINISH RELATIONSHIP report.
UPDATE: Fixed Required Completion dates check.
UPDATE: Activities with changed calendars skipped on Description Change check fixed.
Version 2.74 (April 2003)
DESTATUS: Fixed error in documenting version number if default directory is not used.
DESTATUS: Multiple User-interface improvements.
SAPRO: Splash no longer moves on open.
UPDATE: Fixed version number problem (cosmetic.)
UPDATE: Changed float vales reported from Target Schedule to that of Update Schedule.
DESTATUS: Modified Steps 3 & 4 to make it easier to understand and use.
UPDATE: Fixed subtle error with calendar changes causing false positives in modified budgets.
Version 2.73 (February 2003)
DESTATUS: Added Bad Retained Logic check and report.
UPDATE: Open relationship files early for new correlations.
UPDATE: Improved Added As-Built Activities Report.
UPDATE: Sped-up processing of newly completed activities Reports.
ALL: Added voice advisors.
Version 2.72 (January 2003)
ALL: Fixed Menu to allow for alternate (XP) Windows Calculator location
ALL: Added P3 PFXW program to calculator menu. Added log display after run.
ALL: Internal Consolidation of environment-reading into one routine.
LOGGER: Improved accuracy of log updating.
UPDATE: Added Activity Type to several of the existing activity reports.
UPDATE: Added Activities with Changed Activity Types Report.
LOGGER: Added Activity Type Change Report.
Version 2.71 (December 2002)
ALL: Added Free Memory watch on analysis window title bars.
ALL: Bullet-proofed opening of first schedule for Error 76, File or Directory Not Found."
UPDATE: Improved internal memory management.
BASELINE: Vastly Improved Memory Management by swapping code sections in memory.
Version 2.70 (November 2002)
UPDATE: Improved descriptions in relationships reports.
ALL: Force first time users to enter P3 User ID before proceeding further.
BASELINE: Improved Activity Code Check routines.
Version 2.69: (November 2002)
BASELINE: Updated "How To Review" Tips in Help file to reflect Primavera 2002 Conference presentation.
BASELINE: Added Activities without Predecessors Report.
BASELINE: Added Activities without Successors Report.
BASELINE: Added Review Activities With Missing Successors Report.
LOGGER: Added Activities without Predecessors Report.
LOGGER: Added Activities without Successors Report.
LOGGER: Added Review Activities With Missing Successors Report.
ALL: Added directory check for path names longer than 64 characters in length.
Version 2.68: (August 2002)
ALL: Moved "P3 is still running" message to foreground of all windows.
UPDATE: Improved Sub-Project processing.
UPDATE: Improved directory changing error handling.
UPDATE: Improved the working of the Windows Calculator call.
Version 2.67: (August 2002)
APAB: Added message to teach user exactly what to do if calendar late or early messages appear.
ALL: Fixed main window button labels in accordance with AACE Cost Engineer review criticism.
APAB: Fixed error where program erroneously says calendar must be made later.
PROFILER: Fixed Version Box (cosmetic.)
Version 2.66: (August 2002)
BASELINE: Improved date handling past the year 2050.
BASELINE: Bullet-proofed statistical data section.
UPDATE: Improved date handling past the year 2050.
PROFILE: Improved Edit Share (if max number of dates used.)
REBUILDER: Status Milestones better.
REBUILDER: Added warning about P3 calendar errors and Constrained Project Completion Dates.
DESTATUSER: Added warning about P3 calendar errors and Constrained Project Completion Dates.
REBUILDER: Fixed Error 54 on Trial Software only.
DESTATUS: Fixed Error 54 on Trial Software only.
Version 2.65: (May 2002)
UPDATE: Improved the way the MODIFIED ACTAUL DATES Report handled milestones.
PROFILE: Added Export/Import Edit spreadsheets.
PROFILE: Added error recovery to Export/Import Edit Spreadsheets.
Version 2.64: (May 2002)
APAB: Subtle change in converting FS and SF work days.
APAB: Added Weather Holiday note at the end of the run.
UPDATE: Bullet-proofed high level report for odd occurrences.
UPDATE: Added note to Planned Activities with Changed Durations Report explaining odd results.
DESTATUS: Made it more clear that run was over.
Version 2.62: (May 2002)
ALL: Fixed where VIEW and PRINT would not automatically highlight the first report.
BASELINE: Added a second report to display all other lags after existing report to display only odd ones.
Version 2.60: (May 2002)
BASELINE: 'Bullet-Proofed' View Screen if more than 32,000 lines are to be displayed.
DESTATUS: Made Milestones in created schedule 'behave' better.
Version 2.59: (April 2002)
DESTATUS: Added current Physical Memory/Virtual Memory display in upper right of view window during processing.
Version 2.58: (April 2002)
DESTATUS: Added additional status indication during processing.
DESTATUS: Sped-up Updating records for Activity Types routine.
DESTATUS: Added F4-Key to stop diagnostics display listing to help stretch memory for really big schedules.
Version 2.57: (April 2002)
UPDATE: Active Activities Without a Finish Relationship Report
BASELINE: Activities Without a Finish Relationship Report
Version 2.55: (March 2002)
DESTATUS: Added status of activity activation/deactivation to progress screen.
DESTATUS: Confirm Autocost Rule #1 set to link Remaining Duration and % Complete.
DESTATUS: Added optional Work Profiler functionality to program.
DESTATUS: Added better first-day accuracy to some activities.
DESTATUS: Cleaned-up some orphaned Expected Finish Constraints.
SAPRO: Rearranged buttons and layout. Animated splash screen.
Version 2.54: (March 2002)
REBIULD: Added Work Profiler functionality.
REBIULD: Improved process documentation in report.
REBIULD: Added Create One Schedule function with advanced ‘date-picker’ tool.
ALL: Increased font and button size and reformatted all screens for better readability.
Version 2.53: (March 2002)
REBIULD: Improved readability of all screens.
REBIULD: Added Notes to each function explaining how to use.
Version 2.52: (February 2002)
UPDATE CHECKER: Improved ACTIVITIES WITH CHANGED CALENDARS Report.
UPDATE CHECKER: Added LONGEST PATH Report.
Version 2.51: (January 2001)
ALL: Added "Drag and Drop" capability to allow you to drag text directly into your word processor.
Version 2.50: (January 2001)
DESTATUS: Added calendar error analysis section to correct for odd schedules.
DESTATUS: Added Start Calendar Early and Finish Calendar Late settings to overcome odd schedules.
ALL: Increased font size on all Select Project, Select Schedule, and Reports View windows. Now all are resizable.
Version 2.49: (January 2001)
UPDATE: Sped-up ACTIVE ACTIVITIES WITH NO PROGRESS Report.
ALL: Added right-click edit menu to reports.
ALL: Cleaned-up the look of the opening screen.
Version 2.48: (January 2002)
DESTATUS: Added option to have SA Pro delete all constraints.
DESTATUS: Automatically delete all Suspended/Resume & Expected Finish dates.
Version 2.46: (November 2001)
SAPRO: Added Backup & Restore.
DESTATUS: Print out Unexpected Event notice when reached on the output report.
Version 2.45: (November 2001)
ALL: Re-wrote SA Pro Manual with Index.
Version 2.44: (November 2001)
BASELINE: Speeded-up and improved INTERRUPTIBLE ACTIVITIES Report.
BASELINE: Added MULTIPLE RELATIONSHIPS Report.
ALL: Sped-up View Report on Screen.
Version 2.43: (November 2001)
BASELINE: Added Standards Check.
Version 2.42: (November 2001)
BASELINE: Added hard-coded swear words check to Exception Words check.
Version 2.40: (October 2001)
UPDATE: Added the ACTIVITIES WITH ACTUAL STARTS AND NO PROGRESS Report.
UPDATE: Added the ACTIVITIES WITH PROGRESS BUT NO START DATE Report.
UPDATE: Added the SUSPENDED ACTIVITY WITH PROGRESS Report.
UPDATE: Added Suspend/Resume Checks to MOST CRITICAL Report Database.
Version 2.39: (September 2001)
UPDATE: Added ACTIVE ACTIVITIES WITH NO PROGRESS Report.
Version 2.38: (September 2001)
BASELINE: Added Report Analysis Tips to Baseline Help, added direct button and Help Menu.
SAPRO: Added Setting-up SA Pro video.
Version 2.37: (September 2001)
ALL: Added Videos to On-Line Help screens.
ALL: Added P3 User ID Input Box with video.
Version 2.36: (August 2001)
BASELINE: This program now works on subprojects.
UPDATE: Added OUT OF DATE EXPECTED FINISH Report.
Version 2.35: (Fixes all interface problems with WIN NT/2000/XP)
ALL: Added support for network drives.
ALL: Rewrote Batch routine to run faster and better (especially for Win NT & Win 2000.)
Version 2.33: (July 2001)
UPDATE: Added Escape option to DUE DILIGENCE Report.
Version 2.31: (June 2001)
UPDATE: Added MODIFIED ORIGINAL DURATIONS Report.
Version 2.30: (May 2001)
UPDATE: Added MILESTONES AWAITING STATUS Report.
Version 2.29: (April 2001)
ALL: Print out Company Name at the top of all reports.
Version 2.26: (April 2001)
ALL: Work with long file names.
UPDATE: Improved Calendar checking for hourly schedules.
Version 2.25: (2000)
BASELINE: Added Suspicious Remaining Duration checks.
Version 2.23: (2000)
UPDATE: Added Escape check for INTERRUPTIBLE RELATIONSHIPS and MODIFIED COSTS Reports.
UPDATE: Optimized Cost Section to run significantly faster.
Version 2.22: (2000)
APAB: Add SUSPENDED/RESUMED DATES Report.
APAB: Automatically delete out Suspend/Resume Dates.
UPDATE: Added better actual date support for hourly schedules.
Version 2.19: (2000)
UPDATE: Added 3 Suspended/Resume Date Reports (DELETED/ ADDED/ MODIFIED.)
APAB: Added UPDATED RELATIONSHIPS Report.
ALL: Added ability to work with for Long File Directory Names.
BASELINE: Added NON-OVERLAPPING LAGS Report.
UPDATE: Added NEW ORPHANED ACTIVITIES (NO SUCCESSORS) Report.
Version 2.18: (2000)
UPDATE: Added ACTUAL DATES BEFORE TARGET DATA DATE Report.
UPDATE: Added ACTUAL DATES AFTER UPDATE DATA DATE Report.
Version 2.17: (2000)
BASELINE: Added ACTIVITY ID CHECK, NUMERIC WITH BLANKS Report.
BASELINE: Added ACTIVITY ID CHECK, NUMERIC IDS Report.
BASELINE: Added ACTIVITY ID CHECK, ALPHA/NUMERICS WITH LEADING BLANKS Report.
BASELINE: Added ACTIVITY ID CHECK, IDS WITH EMBEDDED BLANKS Report.
BASELINE: Added DUPLICATE ACTIVITY DESCRIPTIONS Report.
BASELINE: Added SUBMITTAL ACTIVITIES WITHOUT SUCCESSOR REVIEW ACTIVITIES Report.
UPDATE: Added recursive potential float check for ADDED AS-BUILT ACTIVITY Report.
Version 2.16: (2000)
BASELINE: Allow for project names longer than four letters.
BASELINE: Add maximum length of report (number of activities.)
BASELINE: Early bailout if Max List length exceeded in the Multiple Near Critical Activities & Interruptible checks.
UPDATE: Changed calendar listing to only print-out changed lines.
Version 2.15: (1999)
UPDATE: Added memory management to reduce memory requirements while running.
Version 2.12: (1999)
BASELINE: Added RESERVED WORD CHECK for Activity Codes and Cost Codes reports.
Version 2.11: (1999)
DESTATUS: Added Longest Path option.
UPDATE: Split Deleted Activities Check into three reports: AS-BUIILT, IN-PROGRESS, and PLANNED Reports.
UPDATE: Split Added Activities Check into three reports: AS-BUIILT, IN-PROGRESS, and PLANNED Reports.
Version 2.08: (1999)
BASELINE: Added Near Critical Setting to reports.
BASELINE: Make Activity Analysis Parameters User-Programmable.
Version 2.06: (1999)
UPDATE: Added (don't print) Report Options.
UPDATE: Added auto increment of report name to prevent overwriting of old report when repeating analysis.
UPDATE: Improved Calendar Report for quick scan.
Version 2.04: (1999)
UPDATE: Added ACTIVITIES WITH ODD TOTAL FLOAT CHANGE (GREATER THAN # OF DAYS OBSERVED) Report.
Version 2.03: (1999)
BASELINE: Halved time to run MULTIPLE CRITICAL PATHS Report.
Version 2.01: (First General Release of Version 2, 06JAN99)
Version 1.10: (First General Release of Version 1, 10APR98)