Baseline Schedule Analysis (review of any single schedule.) Hours mentioned here included multiple reviews per project (review/ rejection/ re-submittal/ re-review/ etc.) Travel time is not included.
Large roadway project. Baseline acceptance required 2 meetings and 3 reviews. Total billable: 41.5 hours.
Medium-sized roadway project. Baseline acceptance required 2 meetings and 2 reviews. Total billable: 29 hours.
Medium-sized widening and soundwalls project. Required 1 meeting and 3 reviews. Total billable time: 15.5 hours.
Medium/small interchange project. Acceptance required 1 meeting and 3 reviews. Total billable time: 6.5 hours.
Internet, one-time analysis. Reviewed schedule without plans/specs. Total billable time: 3 hours.
Schedule Update Analysis (changes from one schedule to the next.) Hours listed here are average hours per update acceptance. This also includes meeting, some Claims Avoidance, and Delay Analysis work. Travel time is not included.
Large roadway project. Average update requirement was 17.7 billable hours.
Medium-sized roadway project. Average update review time was 5.9 billable hours
Medium-sized widening and soundwalls project. Average update review was 6.5 hours.
Medium/small interchange project. Average (sporadic) update review time was 7.2 hours.
Internet, one-time analysis. Reviewed updates without plans/specs. Billable: 3 hours.
Note: Only the five most-recent projects representing the Owner are listed here.